Standard Building Contract
The Joint Contracts Tribunal (JCT) was formed by the Royal Institute of British Architects (RIBA) In 1931 when the first JCT standard form of building contract was issued (although the forms were not referred to as ‘JCT’ until 1977). JCT became a Limited Company in 1998. It now produces a range of standard forms of contract for the construction of buildings accompanied by guidance notes and other standard forms of documentation.
The JCT Standard Building Contract is intended for large or complex construction projects, procured via the traditional procurement route, where detailed contract provisions are needed.
The 2016 edition was released on 4 November 2016. New features include:
- Incorporation of the provisions of the JCT Public Sector Supplement 2011.
- Adjustments to reflect the Construction (Design & Management) Regulations 2015 and the Public Contracts Regulations 2015.
- Amendments to the works and existing structures insurance provisions.
- Revision and simplification of the Section 4 Payment provisions.
- Provisions for the grant of Performance Bonds and Parent Company guarantees.
- Revisions to the way the requirements for Collateral Warranties are set out.
- Incorporation of the provisions of the JCT 2012 Named Specialist Update.
The 2016 edition includes the following documents:
- Standard Building Contract With Quantities (SBC/Q).
- Standard Building Contract Without Quantities (SBC/XQ).
- Standard Building Contract With Approximate Quantities (SBC/AQ).
- Standard Building Contract Guide (SBC/G).
- Standard Building Sub-Contract Agreement (SBCSub/A).
- Standard Building Sub-Contract Conditions (SBCSub/C).
- Standard Building Sub-Contract with sub-contractor’s design Agreement (SBCSub/D/A).
- Standard Building Sub-Contract with sub-contractor’s design Conditions (SBCSub/D/C).
- Standard Building Sub-Contract Guide (SBCSub/G).
- Standard Building Contract With Quantities (SBC/Q) Tracked Change Document.
- Standard Building Contract Without Quantities (SBC/XQ) Tracked Change Document.
- Standard Building Contract With Approximate Quantities (SBC/AQ) Tracked Change Document.
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Collateral warranty.
- Construction contract.
- CPC2013.
- FIDIC.
- Intermediate Building Contract.
- JCT.
- JCT Design and Build Contract.
- Key dates.
- Latham report.
- Management Building Contract.
- Minor works.
- Modifying clauses in standard forms of contract.
- NEC3.
- Procurement route.
- Standard form of contract.
- Sub-contract.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.