Standard Building Contract
The Joint Contracts Tribunal (JCT) was formed by the Royal Institute of British Architects (RIBA) In 1931 when the first JCT standard form of building contract was issued (although the forms were not referred to as ‘JCT’ until 1977). JCT became a Limited Company in 1998. It now produces a range of standard forms of contract for the construction of buildings accompanied by guidance notes and other standard forms of documentation.
The JCT Standard Building Contract is intended for large or complex construction projects, procured via the traditional procurement route, where detailed contract provisions are needed.
The 2016 edition was released on 4 November 2016. New features include:
- Incorporation of the provisions of the JCT Public Sector Supplement 2011.
- Adjustments to reflect the Construction (Design & Management) Regulations 2015 and the Public Contracts Regulations 2015.
- Amendments to the works and existing structures insurance provisions.
- Revision and simplification of the Section 4 Payment provisions.
- Provisions for the grant of Performance Bonds and Parent Company guarantees.
- Revisions to the way the requirements for Collateral Warranties are set out.
- Incorporation of the provisions of the JCT 2012 Named Specialist Update.
The 2016 edition includes the following documents:
- Standard Building Contract With Quantities (SBC/Q).
- Standard Building Contract Without Quantities (SBC/XQ).
- Standard Building Contract With Approximate Quantities (SBC/AQ).
- Standard Building Contract Guide (SBC/G).
- Standard Building Sub-Contract Agreement (SBCSub/A).
- Standard Building Sub-Contract Conditions (SBCSub/C).
- Standard Building Sub-Contract with sub-contractor’s design Agreement (SBCSub/D/A).
- Standard Building Sub-Contract with sub-contractor’s design Conditions (SBCSub/D/C).
- Standard Building Sub-Contract Guide (SBCSub/G).
- Standard Building Contract With Quantities (SBC/Q) Tracked Change Document.
- Standard Building Contract Without Quantities (SBC/XQ) Tracked Change Document.
- Standard Building Contract With Approximate Quantities (SBC/AQ) Tracked Change Document.
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Collateral warranty.
- Construction contract.
- CPC2013.
- FIDIC.
- Intermediate Building Contract.
- JCT.
- JCT Design and Build Contract.
- Key dates.
- Latham report.
- Management Building Contract.
- Minor works.
- Modifying clauses in standard forms of contract.
- NEC3.
- Procurement route.
- Standard form of contract.
- Sub-contract.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.